Phased Live Environment Transformation of a Live 42,000ft² Health Club
​
Client: David Lloyd Leisure
Main Contractor & PSCS: Built
Location: Beech Hill Road, Clonskeagh
Sector: Leisure & Wellness
Programme: 6 to 38 weeks (across multiple zones)
Size: 42,000 ft²
Project Overview
Built were appointed to deliver the phased refurbishment and reconfiguration of David Lloyd Leisure’s flagship Clonskeagh facility - an operational 42,000ft² health club serving over 7,000 members. The project involved the redevelopment of multiple zones including spa, fitness, reception, DL Kids, bar and club room, changing areas, and pool facilities - all while maintaining live operations with minimal disruption to members and staff.
The project was delivered using our BUILT360 methodology, a fully integrated delivery model designed to ensure zero-disruption construction, rigorous health and safety compliance, and seamless stakeholder communication within complex, live environments.
Scope of Works
Spa
Complete demolition and rebuild of an existing studio area to create a high-spec wellness zone. New facilities included Hydro and Plunge Pools, Deep Relax Rooms, Crystal and Citrus Steam Rooms, Finnish Sauna, Himalayan Salt Sauna, feature showers, foot spa, and heated relaxation beds.
​
Fitness Studios
Conversion of an indoor tennis court into four Blaze Studios, comprising High-Impact, Mind & Body, Spin Cycle, and a Blaze Waiting Area. Works included feature access stairs, new lift installation, and full AV/lighting integration.
​
DL Kids
Creation of a dedicated children’s play area with upgraded finishes to walls, floors and ceilings. Delivered in a focused six-week programme to enable early handover.
​
Bar & Club Room
Full strip-out and fit-out including new kitchen and bar installation, custom joinery (pods and booths), and new finishes throughout. Programme sequenced to follow DL Kids completion.
​
Reception
Upgrade to all finishes, new reception desk, breakthrough access to the new Fitness Studios, and installation of new glazing and doors. Coordinated with Bar fit-out for seamless transition.
​
Pool & Change Areas
Refurbishment of the existing pool zone and reconfiguration of sauna/steam rooms into a poolside relaxation area. Full strip-out and upgrade of changing rooms, with new M&E, lockers, vanity units, DAC toilets, and high-quality finishes.
Key Challenges & Innovations
-
Live Environment Execution
All works were delivered while the facility remained open to members, requiring tight scheduling and phased handovers to avoid disruption.
-
Phased Programme Coordination
Each zone followed a staggered timeline, with interdependent sequencing across spa, fitness, and social spaces.
-
Stakeholder Engagement
Frequent communication with David Lloyd management and on-site teams ensured safe operations and real-time decision-making throughout the build.
Results & Outcomes
-
Project completed on schedule across all phases
-
High member satisfaction with minimal operational disruption
-
Significant upgrade to wellness, fitness, and social facilities
-
Strong reinforcement of Built’s reputation in live, complex refurbishment projects
Conclusion
David Lloyd Leisure Clonskeagh exemplifies Built’s ability to deliver complex, phased upgrades in fully operational environments. Using the BUILT360 methodology, the project was executed with precision and care, transforming an ageing leisure facility into a modern, multi-functional destination for fitness, relaxation and community.